0 Replies Latest reply on Jul 21, 2011 11:21 AM by Sybil Sheppard

    Tracking Cost Changes in an RFP

    Sybil Sheppard Master

      Hello!

       

      We are looking for a way to track cost changes (usually due to development costs) on an RFP over the course of the build.  For example, the initial RFP will have cost submitted for parts, tooling, packaging and development.  We want to maintain that cost from the initial proposal, but as the awarded supplier begins to develop the final product the cost often changes and can change multiple times before the product is in its final state.  We were looking at alternative bidding as a way to capture this data but are still weighing the pros and cons.  Any suggestions you have would be greatly appreciated!  Thank you for your time